Hawks Ridge Residents, as a follow up to previous posts related to landscaping plans for 2017 and beyond in the community, we are pleased to share the schedule below, and map image that outlines the work planned for this year and what is scheduled in future years. As is the nature of seasonal work, these timelines are subject to change based on weather conditions:
 
Pathway construction – May 23 to June 30, 2017
Fencing – June 30 to July 30, 2017
Landscaping (plant material etc.) – July 30 to August 15, 2017
 
We have also had several inquiries about the damage to the entry feature – the sign contractor has been notified and is prepared to be on site within two weeks to complete the repair. There is a temperature requirement for this repair to be completed, and is therefore also weather dependent.